Carrying out all DSLAM station wiring till power up and station integration in the network. Describing the steps of our work in this project beginning with cables laying on the trays, connecting them between blocks and the rack and then tied the Data cables.
Showing our steps as the following:
1-cables laying:
Laying cables between blocks and the DSLAM.
2-punch cables to the blocks:
Working on all types of blocks preparing cables
and forming the blocks to punch cables to the blocks.
3-tying cables:
Tying cables with high quality and high accuracy.
4-connecting the cables onto the Rack:
Entering the cables of subscribers on the rack and connecting them to the cards.
5-connecting the electrical power:
Connecting the electrical cables to the rack to power up the DSLAM.
|